University of Maryland New Dental School & Teaching Facility

606 Redwood Street, Baltimore, Maryland 21201

Description

160,000 Sq. Ft. New Construction of Multi-Story Building with BSL3 labs, laboratories, classrooms and offices. 

Scope of Work/Challenges to Project

Subcontractor. Install electrical work per Division 16000 plans and specifications and according to National Electric Code.

This was a large 12-story teaching lab facility. A 1500kW Generator had to be disassembled and lifted to the roof via crane to be reassembled. This project was heavy on power installation to accommodate the laboratories. A 4000A service had to be tied-in from the existing campus substation.

The telecommunications package alone was worth 1 Million dollars. Project management and strong on-site supervision enabled constant coordination and with other trades and the general contractor. Due to the company’s size, Enterprise Electric Company was able to provide adequate manpower to keep the project moving.